Environment Effects Statement (EES)
VNI West is required to complete an Environment Effects Statement (EES), and obtain relevant Victorian and Commonwealth approvals, before construction can begin. An EES describes the proposed project, its rationale, potential environmental and social effects and how VicGrid VNI West proposes to avoid, mitigate or manage environmental effects. The Victorian Department of Transport and Planning (DTP) administers the process on behalf of the Minister for Planning.
The VNI West EES is prepared in accordance with the Ministerial guidelines for assessment of environmental effects under the Environment Effects Act 1978 (Vic) and the scoping requirements issued by the Minister for Planning. A draft Planning Scheme Amendment (PSA) GC316 is also being prepared in accordance with the Planning and Environment Act 1987 (Vic).
Preferred Easement
Preferred Easement for VNI West Report
-
Preferred Easement for VNI West Report
The VNI West project has released the preferred easement for the Victorian section of the VNI West transmission line project.
The process to refine the initial 50km wide area of interest to a 2km draft corridor and now a 70m preferred easement has been shaped by 18 months of consultation with communities and individual landholders, along with field studies and technical and engineering assessments.
Draft Corridor
Draft Corridor for VNI West Report
Environmental Constraints
-
Environmental Constraints Summary Report
To provide some insight into the work under way to refine the route for VNI West, we are sharing a series of maps and analysis, which illustrate the important areas of land use across the broad area of interest for VNI West.
Regulatory Investment test for Transmission
Regulatory Investment Test for Transmission (RIT-T)
Engagement and Consultation Summary
Engagement and Consultation Summaries
-
Tragowel and Murrabit Event Summary Report
On the 29th and 30th of October 2024, from 5pm-7pm, the VNI West project team held an information session for landholders and near neighbours in Murrabit and Tragowel.
A presentation was shared at the session and attendees were able to ask questions or provide feedback throughout.
-
Community Events Summary
April 2024
From 16 to 18 April 2024, the VNI West project team held community drop-in sessions at Charlton, Kerang and Stawell – key central locations within the VNI West draft corridor area. These drop-in sessions were attended by close to 150 people.
-
Murrabit Community Meeting Summary
March 2024
On 27 March 2024, the VNI West project team held a roundtable with landholders and community members in Murrabit. The meeting was in response to requests from local landholders for a group meeting and provided an opportunity to hear directly from those in the local area. This document provides an overview of the key themes raised by attendees and the project's response.
-
Tragowel Community Meeting Summary
February 2024
On 27 February 2024, the VNI West project team held a community roundtable with landholders and community members in Tragowel. This document provides an overview of the key themes raised by attendees and the project's response.
-
Community Event Summary Report
October 2023
Between 10 and 19 October 2023, the VNI West project team held six community information sessions including a webinar, attended by close to 500 people.
The purpose of this report is to provide a summary of the outcomes of this engagement and respond to common items of community concern.
-
Interactive Map Summary
August 2023
An interactive map was open for public comment between 27 May to 2 August 2023 (9.5 weeks). Participants were able to submit comments for consideration through this online tool or call the project team to add comments.
A total of 4,009 stakeholders and community members visited the map. Of these, 201 users provided a total of 2326 comments. The interactive map was promoted through project updates, social media, newspapers and in person at community events.
-
Community Events Summary
July 2023